14.05.08 Update an ITR Enrolment

Once the enrolment is confirmed by the ITR. The ITR Status will show “ITR Active” and when in Edit mode, the green Enrolment Actions button will have multiple more functions highlighted in red:

Graphical user interface, text, application, email

Description automatically generated

The functions are used as below:

  • Send ITR Update Simple Enrolment

Enrolments can be updated through the update simple and complex programme functions in ITR. The only information that can be changed when updating an enrolment is the learner enrolment date in the programme. You can also add unit standards or remove nonmandatory unit standards from the enrolment. This includes additional unit standards for complex apprenticeships and unit standards associated with sub-programmes. If there is a need to change other information associated with the enrolment, you will need to either withdraw and re-enter the programme enrolment or delete the entire enrolment.

  • Send ITR MA NZA TA or Update Training Agreement message

Update a training agreement Provided the training agreement is not FINISHED, the elements in list below are updatable on the Update Training Agreement message: Where a learner has changed employer, use the transfer employer message to report the new employer details. This enables accurate reporting and analysis of learner history. Alternatively, the enrolment can be withdrawn and re-created; however, this is not the recommended method.

  • Elements:
    • Employer Head Office Name
    • Employer Sub Division Name
    • Employment Location TLA Code
    • Industry Code
    • MoE Exemption Code
    • Employment Type Code
    • Prior Activity Code
    • Training Agreement Signed Date
  • Transfer Programme

When a new programme version was created, manually transfer the enrolment to a new programme version with this message.

Related Articles

14.05.10 Complete ITR Enrolment

The ITR determines whether a programme enrolment is to be COMPLETED or not. This process is done on a daily basis through the ITR completions service. It runs at approximately 5am each morning. ITR enrolment cannot be completed in SELMA until is completed in ITR. Once a student has achieved all components in an enrolment, …

14.05.13 Record MAC Visit

Record a MAC Visit MAC visits can only be recorded and sent from the students’ enrolment. Go to the Event Log tab and create a new note of type MAC Visit as shown below. This will send a MAC visit message to the ITR upon clicking the “Add Event” button. If you delete the event …

2025 DXP SDR

SDR Changes SELMA has implemented a new feature and introduced new fields to align with the latest DXP SDR. Below is the summary of the field changes in the DXP SDR. For detailed specifications and implementation guidelines, please refer to the official TEC documentation at Data Specifications for the Single Data Return – Data System …

14.05.02 New Programme Version

New programme versions are required when the credit value, the nominal duration or the target qualification number, strand or version changes. In registering a new version of a complex programme, the sub-programmes must have the same programme number as previous versions. The sub-programme versions may differ. The only field that can be changed on a …